Project Summary:
The Air Force is committed to improve
the ecological health of an off-base pond being impacted by a sewage plume as part of its
overall environmental cleanup program. A P rich groundwater plume that originates from a
former MMR wastewater treatment plant, discharges to a state-owned glacially formed kettle
hole pond. The plant operated for more than
50 years leaving a large mass of P sorbed to sandy soils upgradient of the pond. This mass of P has been found to desorb very
slowly from the aquifer in an anoxic setting formed by microbial degradation of other
sewage related compounds. Current P loading
is estimated to be 100-200 kg/yr and is expected to completely discharge to the pond
through a very small zone of its bottom sediments in 20 to 30 years. Continued P discharge to the pond is expected to
produce an increased frequency of blue-green algae blooms.
The installation of a geochemical barrier in the P discharge zone
(footprint) is expected to significantly reduce P loading to the pond, thereby enhancing
its overall ecological health. The
geochemical barrier project was a final step in P remediation for the pond following
closure of the plant in 1995 and a hypolimnetic alum treatment in 2001.
AFCEE installed the geochemical barrier in the
top three feet of pond sediments along 300 feet of the northwest shoreline of Ashumet Pond
and it extended 40 feet out into the pond. The
project was installed in August and September of 2004.
The project consisted of excavating approximately three feet of pond
sediments, mixing the sediments with zero-valent iron (ZVI) and then placing the mixture
back in the excavated areas. The surface was
then contoured to match the original shoreline elevations.
Permits for this project were obtained from the Falmouth Conservation
Commission, the U.S. Army Corps of Engineers and the Massachusetts Department of
Environmental Protection.
Scientists from the U.S. Geological
Survey (USGS) explained the results of preliminary monitoring work conducted in September
and November at the December 8, 2004 meeting of the Plume Cleanup Team (PCT). Two rounds of post-installation sampling have been
performed and more data collection over the next several years will allow for a more
detailed evaluation of barrier performance. Preliminary
data collected just after barrier installation and in November 2004 suggests substantial
removal of P from the plume.
Much research and discussion was done
cooperatively with scientists, permitting agencies and the local community to develop an
effective science-based strategy that was both permitable and publicly acceptable. Numerous public meetings, Ashumet Pond Nutrients
Advisory Group (APNAG) and PCT meetings, were held by the Air Force in each step of the
research process to keep the local community informed.
This approach allowed the Air Force contractors to provide scientific
information in small digestible pieces that could easily be understood in an evening
meeting. The USGS and Air Force contractors
will continue monitoring barrier performance, the movement and eventual dissipation of the
P groundwater plume, discharge zone concentrations and pond water quality. Results of this work will continue to be presented
at PCT meetings and posted on this website. An
update of the construction and monitoring of the iron barrier will be presented at an
APNAG meeting in Spring 2005.
Reports:
Notice Of Intent Application for the
Ashumet Pond Geochemical Barrier, 2004 - NOI for Ashumet Pond
Barrier.pdf 
Ashumet Pond Phosphorus Inactivation Report, February 2002 - Ashumet Final
Report.pdf
USGS Presentation, December 2004 - Monitoring Discharge
of the Phosphorus Plume to Ashumet Pond
Ashumet Pond Nutrients Advisory Group - APNAG |