Schedules:
Ashumet Pond
Iron Barrier Project Schedule
Revised
8/16/04
The Ashumet
Pond iron barrier installation work will begin on Monday August 9, 2004 and is expected to
be completed by Friday, September 3, 2004. Work will be conducted Mondays through
Thursdays, from 7 a.m. to 5 p.m., with ½ hour equipment setup starting at 6:30 a.m.
The proposed
schedule for the installation work is as follows:
8/9/04 8/12/04: (Completed)
- Install Dura-base mats along shoreline
- Install silt-barriers in pond and along shoreline
- Place pumps with secondary containment along shoreline
- Install Aqua-barriers along shoreline and inflate with pond water
8/16/04 8/19/04:
- Continue to install Aqua-barriers along shoreline and inflate with
pond water
- Set-up sump pumps and bag filter for de-watered area
- De-water the first section of the barrier area
- Perform pre-excavation survey of pond bottom elevations
8/20/04 8/22/04:
- Continue to de-water first section of barrier area
8/23/04 8/26/04:
· Excavate pond
sediments, screen, mix with iron and backfill first section of barrier area
- Repeat the above actions (aqua barrier, de-water, excavate and
backfill) for the second section of the barrier area
8/30/04 9/2/04:
- Deflate/drain Aqua-barriers and remove from pond
- Perform post-excavation survey of pond bottom elevations
- Collect samples of barrier material
- Clean-up aqua-barriers and remove from the site
- Remove Dura-base mats, clean and remove from the site
- Remove all equipment from site and cleanup site area
Enhancing Ashumet
Pond Health with Iron Barrier Work - August 2, 2004. Officials of the Air
Force Center for Environmental Excellence (AFCEE) announced that the installation of an
iron barrier in Ashumet Pond will begin Monday, August 9, 2004. Read More... Post card
|